Key environmental and social milestones of the Project are as follows:
| 01 | Agreement for Preparation and Development of ESIA & RAP | 04/30/2013 |
| 02 | Finalization of ESIA & RAP | |
| 03 | Recognition of Project Location in National Park | 05/03/2013 |
| 04 | Agreement for Carrying out Studies of CHA & BAP | 09/13/2013 |
| 05 | Peer Review Meeting with ADB in Manila | 09/30/2013 |
| 06 | Additional Agreement with Hagler Bailly for Climate Change Assessment Report and Updating the ESIA | 02/27/2014 |
| 07 | Reviews and Objection of ESIA by EPA | 02/28/2014 |
| 08 | Submission of Revised ESIA | 03/31/2014 |
| 09 | Acceptance of ESIA by EPA | 04/09/2014 |
| 10 | Public Hearing | 05/15/2014 |
| 11 | Approval for Construction in National Park | 05/21/2014 |
| 12 | Issuance of Environmental NOC | 06/18/2014 |
| 13 | Baseline Biodiversity Assessment | 09/23/2014 |
| 14 | Biodiversity Action Plan Draft Report | 09/23/2014 |
| 15 | Ecohydraulics Specialist Report | 09/23/2014 |
| 16 | Environmental Flow Assessment | 09/23/2014 |
| 17 | Environmental and Social Management System (ESMS) Framework | 09/23/2014 |
| 18 | Frameworks for Management Plans | 09/23/2014 |
| 19 | Geomorphology Specialist Report | 09/23/2014 |
| 20 | Mitigation Strategies with Respect to the Impact of Sand and Gravel Mining in the Poonch Basin | 09/23/2014 |
| 21 | Physical Baseline | 09/23/2014 |
| 22 | Finalization of Road Map for National Park Management Plan | 09/25/2014 |
| 23 | Finalization of ESIA | 09/25/2014 |
| 24 | Cumulative Impact Assessment | 11/01/2014 |
| 25 | Approval of Wildlife & Fisheries Department, GoAJK for BAP | 01/02/2015 |
| 26 | Agreement for Carrying out Additional Studies for Updating BAP | 01/13/2015 |
| 27 | Agreement for Carrying out Security Risk Assessment, Developing a Security Management Plan and Related Procedures | 01/27/2015 |
| 28 | Security Risk Assessment | 02/15/2015 |
| 29 | ESIA Submission to EPA | 02/20/2014 |
| 30 | Approval of Wildlife & Fisheries Department, GoAJK for updated BAP | 03/11/2015 |
| 31 | Land Acquisition and Resettlement Plan (LARP) | 06/15/2015 |
| 32 | Construction Environmental and Social Management Plan | 09/15/2015 |
| 33 | Emergency Response and Contingency Plan | 09/15/2015 |
| 34 | Biodiversity Action Plan | 10/01/2015 |
| 35 | Stakeholders Engagement Plan | 10/06/2015 |
| 36 | Environmental and Social Management System (ESMS) | 10/06/2015 |
| 37 | EHS Plan for Diversion Tunnels | 10/15/2015 |
| 38 | Fire Emergency Response Plan | 10/15/2015 |
| 39 | Environment, Occupational Health and Safety Program | 10/15/2015 |
| 40 | Muck Disposal Plan | 10/15/2015 |
| 41 | Malaria Management Plan | 10/15/2015 |
| 42 | Spill Contingency Plan | 10/15/2015 |
| 43 | Traffic Management Plan | 10/15/2015 |
| 44 | Waste Management Plan | 10/15/2015 |
| 45 | Agreement for Development of Detailed Livelihood Restoration Plan (DLRP) | 11/17/2015 |
| 46 | Stakeholders Consultation | Ongoing |
| 47 | Finalization of Site Specific Plans | Ongoing |
| 48 | CSR Plan | In Progress |
| 49 | Finalization of Climate Change Assessment Report | |
| 50 | Finalization of Glacier Lake Outburst Floods (GLOF) Assessment | |
| 51 | Approval of Wildlife & Fisheries Department for Execution of BAP Implementation Agreement | 02/19/2016 |
| 52 | Execution of BAP Implementation Agreement | 02/22/2016 |